Concrete Footing Calculator

Convert strip footings and round piers into cubic yards, bag counts, and a ready-mix order. This is a quantity tool — it does not replace a structural engineer or local code.

Use Rectangular Slab for continuous strip footings (length × width × depth). Use Tube / Column for solid piers — leave inner diameter at 0 — or Round Slab for isolated pads.

Units:

Average ready-mix concrete costs $120-$200 per cubic yard.

Enter dimensions above to see your concrete estimate.

How to Calculate Concrete for a Footing

A footing is a volume problem. Measure each run or pier, convert every dimension to feet, then convert cubic feet to cubic yards:

Cubic feet = Length (ft) × Width (ft) × Depth (ft)
Cubic yards = Cubic feet / 27

Width and depth are usually recorded in inches on a plan. For handwritten math, convert those inches to feet (divide by 12) before multiplying. In the calculator above, do not convert the depth: Rectangular Slab takes length and width in feet, and Thickness in inches. It divides thickness by 12 internally.

Strip (continuous) footings

Treat each straight run as a rectangle. Do not average different widths or depths — split the foundation into sections, calculate each one, then add the cubic yards.

Example: a 40 ft strip, 16 in wide and 8 in deep:

  • Hand math — width: 16 / 12 = 1.333 ft; depth: 8 / 12 = 0.667 ft
  • Volume: 40 × 1.333 × 0.667 = 35.56 cubic feet
  • Cubic yards: 35.56 / 27 = 1.32 cubic yards
  • With 10% waste: 1.32 × 1.10 = 1.45 cubic yards
  • Calculator fields: Length 40, Width 1.333, Thickness 8 (inches). Do not type 0.667 into Thickness.

That volume is about 59 bags of 80-lb mix. For anything over about 1 cubic yard, ready-mix is usually cheaper and more consistent than bags.

Pier pads and sonotube piers

Round piers use a cylinder: π × radius² × height. In the calculator, open Tube / Column, enter the outer diameter and height, and leave inner diameter empty (0) for a solid pier. Use Round Slab for a shallow circular pad.

Example: twelve 12 in diameter piers, each 4 ft deep:

  • One pier: π × 0.5² × 4 = 3.14 cubic feet = 0.116 cubic yards
  • Twelve piers: 1.40 cubic yards
  • With 10% waste: 1.54 cubic yards

Waste, bags, and ready-mix

Footing trenches are rarely square. Add 5–10% extra for over-excavation, sloughing, and spillage. Running short on a continuous pour creates a cold joint in the footing.

  • Under ~1 cubic yard: 80-lb bags (about 45 bags per cubic yard) are practical.
  • Over 1–2 cubic yards: order ready-mix. Ask about short-load fees on small truck orders.

Many residential footings use 3000–4000 PSI concrete, but mix, width, depth, frost line, and rebar come from the plans and the authority having jurisdiction — not from this calculator.

What this calculator does not decide

Quantity only. It does not size the footing, choose reinforcement, evaluate soil, or replace a structural engineer, inspector, or building code. Confirm dimensions on the approved drawings before you order.

Footing Calculator FAQ

How do I convert a footing to cubic yards?
For handwritten math, convert width and depth from inches to feet (divide by 12), multiply length × width × depth, then divide by 27. In the calculator, enter width in feet and depth in the Thickness field as inches (8 for an 8-inch footing, not 0.667).
Should I use the slab shape or the tube shape?
Use Rectangular Slab for strip footings and rectangular pads. Use Tube / Column with inner diameter 0 for solid round piers, or Round Slab for a shallow circular pad.
Do I add the wall concrete into the footing total?
No. Calculate the footing and the stem wall as separate rectangles, then add the cubic yards. Mixing widths or heights in one input under- or over-orders the truck.
How wide should my footing be?
This page does not size footings. Width and depth depend on loads, soil bearing, frost depth, and local code. Use the calculator only after those dimensions are known.
Bags or a ready-mix truck?
Bags work for a few pier holes. A continuous strip around a house is almost always a truck order. One cubic yard is about 45 bags of 80-lb mix — heavy to mix by hand in an open trench.